Construction
Fort Bend ISD in Houston Moves Forward with New Aquatics Facility
2024-11-26
In suburban Houston, Fort Bend ISD is making significant strides in its efforts to build a state-of-the-art practice facility for local swimming and diving teams. This comes at a time when a $1.26 billion bond package faced a shortfall of $163.2 million in promised projects. In October, trustees took decisive actions to address the budgetary constraints, including eliminating the construction of a new elementary school and delaying the construction of a transportation facility. They also adjusted fine arts and athletics projects to reduce the overage by $95.9 million, according to local media Community Impact.
Challenges and Choices
Due to the way the bonds were structured, the funds allocated for the swimming pool project could not be diverted to other parts of the bond package. With the pool project already projected to be $6 million over budget, the district had to carefully consider its options. One option was to replicate the existing 50-meter "stretch" indoor pool with three diving boards, which would allow multiple teams to practice simultaneously. This plan was ultimately approved, although administrators explored the possibility of making it an open-air facility to cut costs and building it into a large competition-ready natatorium with spectator seating. However, the latter option would have cost $17 million more than the budgeted amount.Internal Investigation Findings
An internal investigation by the district revealed that Fort Bend ISD administrators did not intentionally mislead voters about the scope of the facility. Instead, they failed to adequately communicate to the board and the public that the project would be a replica of the existing aquatics practice facility. The primary cause of the cost overrun was attributed to administrators not adjusting for inflation when the bond package was postponed from 2022 to 2023.Impact on Contingency Funds
The $6 million cost overrun will have to be covered from the $33.08 million in contingency funds from the 2014 and 2018 bond packages. This decision will have implications for the district's financial reserves and future projects. Despite the challenges, the project timeline remains on track, with construction set to begin in February 2026 and the facility expected to open in June 2027. The facility is designed to withstand the sweltering Bayou summers without mechanical forced air, relying on walls lined with garage doors for ventilation.Current School and Swimming Programs
Fort Bend ISD currently has 12 high schools among its 83 total schools, serving over 80,000 students. The district is currently served by an existing practice facility and the Don Cook Natatorium, which was opened in 1998 as the first indoor 50-meter pool in the Houston area. Eleven of the district's 13 high schools have UIL swimming programs, with most competing in the state's biggest classification, 6A, and two competing in Class 5A. These swimming programs play a crucial role in the district's athletic offerings and contribute to the overall development of students.