Highway 75 in Sioux Center Reopens for Winter; Spring Construction Resumes
2024-11-27
Sioux Center, Iowa is witnessing a significant transformation as the construction on Highway 75 progresses through the winter. After a full construction season, traffic is gradually returning to normal on this crucial route. The re-opening of the section from 9th Street South to 5th Street South on Monday marks an important milestone in the overall project.
"Sioux Center's Highway 75 Rebuild - A Journey to Safety and Function"
Phase 1: 20th St. S to 13th St. S
This year, contractors have made remarkable progress in Phase 1. They have substantially completed the 2/3-mile section between 20th St. S and 13th St. S, near Sioux Center Dental. The work includes paving, the creation of landscaped medians, the installation of streetlights, and the establishment of trail connections. These improvements not only enhance the visual appeal of the area but also provide better access and safety for both motorists and pedestrians.The newly paved sections give a smooth and seamless driving experience, reducing the chances of accidents and improving overall traffic flow. The landscaped medians add a touch of natural beauty to the highway, making it a more pleasant journey for commuters.Phase 2: 13th St. S to 5th St. S
In Phase 2, contractors have been busy with various tasks. They have removed the old pavement and installed new water, sewer, and storm sewer mains and connections. New concrete has been laid from 13th St. S to 5th St. S, north of Kroese & Kroese. Along with this, new sidewalks have been paved, traffic signals have been installed, driveways have been replaced, and work on medians is ongoing.The installation of traffic signals is a crucial aspect of this phase as it helps regulate the flow of traffic and ensures the safety of pedestrians. The replacement of driveways is another important aspect that addresses the needs of the local community.Future Phases and Partnerships
Construction will resume in spring 2025 from 5th St. S to around Central Park, covering a little more than half a mile including downtown Sioux Center. In 2026, contractors will work on the 2/3-mile section from the Central Park area to 12th St. N, near McDonalds. This is a 4-year, 2.5-mile project that involves a partnership between the Iowa Department of Transportation and the City of Sioux Center.The Iowa DOT is also planning an additional Highway 75 improvement project in 2027-28 from 12th St. N to Highway 18 near Hull. Sioux Center is actively participating in the section between 12th St. N (McDonalds) and 20th St. N (near Pella Corp.), which will have two lanes of travel in each direction, turn lanes, landscaped medians, and a pedestrian trail on the east side.These ongoing projects are a testament to the commitment of the authorities and contractors to improve the infrastructure of Sioux Center and make it a more sustainable and livable place. The long-term investment in underground utility replacements will set Sioux Center up well for the future, ensuring the smooth functioning of the city for years to come.