Construction Milestones: Foster School Project Stays on Track Despite Challenges
2025-01-29
Despite encountering unexpected obstacles, the renovation of Foster School in Evanston's Fifth Ward remains well within its allocated budget and timeline. The project, managed by District 65, is set to conclude by mid-2026, with key milestones already achieved.

Building a Bright Future for Students and Staff

The construction of Foster School has faced several unforeseen challenges, yet it continues to progress smoothly. Officials have reassured stakeholders that the project will stay within its $48.5 million budget, thanks to strategic adjustments and careful management. One significant issue involved the stabilization of the site’s soil, which required additional resources but ultimately ensured the foundation's integrity.

Navigating Unexpected Challenges

During the initial phase of ground improvement, contractors encountered equipment sinkage due to unstable soil conditions. This necessitated an urgent change order to bring in more stone for stabilization. While this added $117,704 to the budget, it was crucial for ensuring the safety and stability of the construction site. Brian Kronewitter from Cordogan Clark & Associates explained that the contingency for extra materials was initially planned for later stages, but had to be expedited due to the unexpected situation.

This challenge underscored the importance of adaptability in large-scale projects. Despite the unplanned expense, the overall project remained financially sound, with some bid groups even coming in under budget. For instance, the third bid group for mechanical infrastructure saved a substantial $3.5 million, providing a much-needed buffer for future contingencies.

Achieving Key Milestones

The project has reached several critical milestones, including the completion of site clearing and foundational work. The building structure is scheduled to start rising in March, with the foundation expected to be fully completed by mid-April. These achievements reflect the meticulous planning and execution by the project team.

As the construction progresses, the focus now shifts to installing flooring, kitchen facilities, playground equipment, and paving. The final two bid groups cover these elements, ensuring that every aspect of the school is thoroughly addressed. With the project slated for completion by July 13, 2026, staff will have ample time to move into the new facility before the start of the 2026-2027 academic year.

Selecting the Right Leadership

Parallel to the physical construction, the human resources department is actively seeking candidates for the principal position at Foster School. Interviews are set for March, with plans to finalize the selection by April. The chosen leader will commence duties on July 1, allowing them a full year to prepare for the school’s opening.

This extended period is vital for setting up the curriculum, engaging with students and families, and collaborating with the construction team. Charmekia McCoy, chief of academics and schools management, emphasized the significance of having a "planning principal" involved in all discussions. Superintendent Angel Turner also highlighted the importance of this role in shaping the school’s future.

Community Engagement and Input

The Foster School Transition Committee has been instrumental in fostering community involvement. Meetings have focused on discussing essential aspects like school colors, logos, and criteria for selecting the principal. A survey sent to families seeks their input on desired qualities in a school leader, ensuring that the community's voice is heard throughout the process.

This collaborative approach reflects District 65’s commitment to creating a school that not only meets educational standards but also resonates with the community it serves. As the project moves forward, the district remains dedicated to transparency and engagement, ensuring that Foster School becomes a beacon of excellence for years to come.